In our B2B enterprise, we prioritize engaging with a diverse audience, including administrative and purchase officers, institutional clients, suppliers, potential employees, credit agencies, bankers, and other stakeholders. Our dedicated efforts focus on offering a transparent and comprehensive view of our firm, addressing the specific needs of key individuals involved in evaluating us as a vendor or client.

Certificates

Few Representative Projects

 
Client Works Location Area (sft.) Time-frame Scope
PROJECTS IN EXECUTION
HDFC BANK LTD. Back office Chennai 225000 4 months Civil Interiors
DBS Bank Ltd. Zonal Office- South Chennai 42000 6 months Turnkey
Sunflag Steel Corporate Office Nagpur 27000 4 months Turnkey
Paramount Health Corporate Office Mumbai 25000 4 months Design& Build
RBL Bank Ltd. Bank Office Delhi 25000 4 months Design& Build
Piramal Estates Corporate Office Mumbai 14000 2 months Turnkey
Piramal Tech Corporate Office Bangalore 38000 3 months Design& Build
RECENTLY COMPLETED
ONDC Corporate Office Siri Fort, Delhi 10000 2 months Turnkey
Ambit Wealth Pvt. Ltd. Zonal Office Aerocity, Delhi 8000 3 months Turnkey
Aerocity, Delhi Corporate Office Saket, Delhi 24000 2 months Design& Build
LIC of India Zonal Office Mumbai 15000 4 months Design& Build
HDFC BANK LTD. Corporate Office Mumbai 10000 6 months Civil Interiors
EARLIRE REPRESENTATIVE PROJECTS
Ostro Power Corporate Office Delhi- Okhla 35000 2 months Design& Build
Venezuela Embassy Embassy Anand Niketan Delhi 11000 2 months Design& Build
HDFC BANK LTD. Back office Indore 45000 3 months Civil Interiors
RBL Bank Bank Office Airoli, Navi Mumbai 105000 4 months Turnkey
Catholic Syrian Bank Corporate Office Churchgate Mumbai 14000 1 months Design& build
Culture Machine Corporate Office Mumbai & Chennai 35000 3 months Design& build
TV 18 Digital Office Indiabulls Mumbai 45000 3 months Design& build
UTV & U-digital ( Arre TV) Corporate Office Worli Mumbai 20000 3 months Design& build
HSBC Zonal Office- South Chennai 20000 4 months Civil & Electrical

Typical Workplan

 
Start Date End Date
Week 0 2-1 8-1 Receiving client mandate Detailed BOQ submission Base builder liaison Client PO issue Preparation of shop drawings Insurance & Compliance Detailed BOQ submission
FIELD EXECUTION CIVIL WORK & CARPET PARTITIONS STORAGES & FURNITURE DOORS POP & GYPSUM MODULAR CEILING PAINTING ELECTRICAL HVAC LV & DATA
Week 1 9-1 15-1 Lineout Site office Lock & Key to site POP Punning
Week 2 16-1 22-1 Sub floor work POP Punning Raceways & Ceiling Conduits
Week 3 23-1 29-1 Tiles Frame & Single skin Storages & other carpentry LV Cabling
Week 4 30-1 5-2 Second skin finish Ceiling wiring & Cabling Hanging of machines + Ducting
Week 5 6-2 12-2 Gypsum ceiling DUCO & Spray start Partition wiring & back box Ducting finish
Week 6 13-2 19-2 Modular glass partition & doors HArdware install Base prep DB dressing & Lights start Grills & diffusors IT cables pull
Week 7 20-2 26-2 Carpet install System furniture deliver Tiles install Paint start Lights install Commissioining High side terminate & LV fittings
Week 8 27-2 5-3 Carpet install SSystem furniture install Final coat Furniture termination HVAC running Field side termination
Week 9 6-3 12-3 Cleaning & Handover
WRAP UP Snag List MS checking Billing